CBD AND SOUTH EAST LIGHT RAIL UPDATE 21 AUGUST 2015

August 21, 2015

In preparation for the new CBD and South East Light Rail, early works on roadways will be continuing to take place by both the project’s Managing Contractor (Laing O’Rourke) and PPP Contractor (ALTRAC Light Rail).

 

The upcoming works and those currently taking place along the alignment are as follows:

PPP Contractor Works – ALTRAC Light Rail

CBD – 23 August to 11 September 2015 (night time work)

Location Date Time Activities
Eddy Avenue, Rawson Place and Pitt Street intersection
Sunday 23 August to Friday 11 September 2015 NB. On Sunday 23 August works will start from 5pm to minimise saw cutting activities to the first night of work.
Night time works: Sunday to Wednesday 8pm to 5am Thursday nights 9pm to 5am
· Trenching work · Utility treatment work

CBD – 17 July to 17 September 2015 (day and night time work) – ALREADY NOTIFIED

Location Date Time Activities
Alfred Street (between George Street and Loftus Street) George Street (between Alfred Street and Market Street) George Street (between Market Street and Rawson Place) awson Place (between George Street and Pitt Street) ddy Avenue (between Pitt Street and Chalmers Street)
Friday 17 July to Thursday 17 September 2015 (approx. 10 nights work per activity at each location)
Night time works: 8pm to 5am Where possible, work will occur during standard day time hours
Survey work Geotechnical investigations Potholing work

Surry Hills and Moore Park – 17 July to 17 September 2015 (day and night time work) – ALREADY NOTIFIED

Location Date Time Activities
Chalmers Street (between Eddy Avenue and Devonshire Street) Devonshire Street (between Chalmers Street and Crown Street) Devonshire Street (between Crown Street and Bourke Street) From corner Devonshire and Bourke Streets (across Eastern Distributor and Moore Park) to Anzac Parade (corner Anzac Parade and Alison Road)
Friday 17 July to Thursday 17 September 2015 (approx. 10 nights work per activity at each location)
Night time works: 8pm to 5am Where possible, work will occur during standard day time hours
· Survey work · Geotechnical investigations · Potholing work

All roads will remain open during mid week night works with limited localised traffic management in place to assist motorists, pedestrians and cyclists. Access to buildings, driveways and pedestrian footpaths will be maintained.

 

If you have any questions regarding the works or traffic changes please contact the principal contractor for these works, ALTRAC Light Rail, on 0426 825 401 or emailSLRCommunity@acciona.com.au

 

All current works notifications can also be viewed on the Sydney Light Rail website at the following link – www.sydneylightrail.transport.nsw.gov.au/latest/current-works

 

Notification Information HERE